Spring Semester

#28 Final Update

We are excited to share our final update on our IPPD project, where we developed a sensor-based system for backer defect detection in composite structures. Our project has reached its final stages, and we are proud of the progress we… Read More

#25 PID 2

The team has been hard at work after prototype inspection day 2. In terms of accomplishments, we have obtained initial capacitance test data with higher resolution than last semester, thanks to the new electronics and gantry. We have also found… Read More

#18 QRB 1 Week