Today is FDR! We’ve put a lot of effort into this project for the last 8 months, so we’re proud to show off what we’re doing today!
Nearly There!
We’ve been planning this survey for the past couple of weeks, and we finally did it! We got a lot of positive feedback, so the team is incredibly proud of what we did over the course of these two semesters.… Read More
PID Complete
This week, we pretty much finished the project! At least the hardware and software sections of the project. We still have one more survey to run and construct the FDR (final design report). We completed our final PID, which was… Read More
A Fruitful Week
This week was incredible for us! Andrew soldered PCB 3 and tested it with all connections, meaning we have everything for hardware! We now are moving onto waterproofing, and we are thinking of putting the Arduino and PCB into a… Read More
Anticipation of Spring Break
This week we upgraded the UI a little by adding the feature of letting the user add or delete the amount of graphs they want on screen. This is version 2, while version 1 can still be used. Version 1,… Read More
Anticipation of QRB 2
This week we got live pressure readings using the TKinter interface we created. In the next couple of weeks, we plan to expand this to the temperature sensors when they’re connected. We are also planning to develop a rolling table… Read More
Survey 1 Complete!
This week we finally finished survey 1! We got 8 responses, which reflects our work over the past couple of weeks. We have gotten figures of our prototype assembly of 2 minutes and 30 seconds, while the older version of… Read More
First Round of Surveys
This week we got a plan to do our software, starting with a moving graph which we will treat as a sliding window problem. This will be an exciting approach since this will be the first time the team uses… Read More
QRB 1 Down
This week we got our Quarterly Review done and we did really well! We have more of our specifications done in the first month, with 2 or 3 of them needing to be reviewed by a survey, which we are… Read More
Moving On
We’ve finished our first prototype! Now we have to prepare for our first round of surveys starting on February 6th. We have the survey questions drafted, so we’re ready to move and begin testing. The flow meter finally decided to… Read More
We’re Back!
We’re back from Winter Break! We hope everyone had a great Holiday! Over the last week, we have been organizing our schedule for the semester, and we’ve decided on a hard deadline for our product on March 28th! It seems… Read More