Hello everyone!

Continuing from last week, we’ve made some updates to our physical prototype. Our skid’s frame now has a second level! This is important because we plan to store additional components integral to our design on the second level that would have been otherwise to store on the first level with the rest of our work, like our reactor. Enough of a gap was left between the two levels such that taller items like our reactor could fit on the first floor.

Caption: Frame with second level and some sheet metal installed

Next week will be focusing on installation of our subsystems. Now that we have enough space to house all our components, we can now begin placing the sheet metal on the two levels’ floors and store all of our equipment to begin assembly and testing. Things are starting to ramp up, so stay tuned for more updates!